Current status: In progress • Investment: +6.000.000 €

gallery

UPCOMING ACTIONS

Maspalomas Gran Canaria Consortium  signs the agreement with Tragsa for the execution of the project.

You can download an extended version of the information about the LANDSCAPE CONDITIONING PROJECT OASIS PALMERAL DE MASPALOMAS here:

3

chronology

Maspalomas Gran Canaria Consortium  signs the agreement with Tragsa for the execution of the project.

April 3, 2023
April 3, 2023

Authorities officially presented the project’s characteristics. The event took place in the Palmeral Oasis area.

Participatory process with citizens, associations, and the business community to understand the SROI impact of the project.

June 6, 2024
June 6, 2024

The Governing Board of the San Bartolomé de Tirajana City Council approves the building permit.

June 21, 2024
June 21, 2024

Technicians from the Consortium and Tragsa meet to coordinate the project planning.

January, 2025
January, 2025

Preliminary Phase

Preparation of the site by relocating and caring for palm trees, removing invasive species, clearing, cleaning, and installing a perimeter fence.

January, 2025
January, 2025

Reserve Observatory Phase

Included additional removal of invasive species, demolitions, construction of a rock embankment to stabilize the terrain, and installation of a sturdy fence to ensure the area’s protection and security.